ITB Berlin is the world's largest travel trade show, held each March at Messe Berlin and organised entirely around scheduled business meetings rather than public browsing. This guide sets out a twelve month countdown to help you plan a stand around that specific format.
Twelve Months Before the Show
Confirm your participation and register your space with the show organiser. At this stage, decide roughly what kind of exhibitor presence you need: a destination pavilion, a company stand, or a smaller meeting focused space. This is also a sensible time to start shortlisting stand companies, since ITB's fixed March dates mean lead time cannot be extended once the calendar year turns over.
Ten Months Before the Show
Set a stand budget and confirm your target stand size. If you are part of a destination pavilion alongside partner regions or tour operators, confirm shared space arrangements early, since multi zone stands need more coordination between everyone involved.
Eight Months Before the Show
Request quotes from shortlisted stand companies and confirm scope in writing: design, production, meeting furniture, technology and onsite support. Since ITB's format is built around one to one meetings, be specific about how many simultaneous meetings your team expects to hold each day, as this shapes how much enclosed or semi enclosed space the design needs.
Six Months Before the Show
Approve a 3D concept for your stand. At this stage, confirm any structural requirements with the venue, particularly if your stand includes raised flooring, suspended elements or a multi zone layout.
Four Months Before the Show
Finalise materials, graphics and any technology requirements, including screens or demonstration equipment if your stand needs to support live product walkthroughs. Confirm staffing numbers for the show, since ITB's compact schedule of back to back meetings often requires more onsite staff than a browsing focused show of the same size.
Two Months Before the Show
Confirm logistics: transport of stand materials to the venue, storage for printed materials such as brochures or maps, and any co exhibitor registration if partners are sharing your space. Reconfirm your appointment schedule and any technology needed to support it, such as booking or meeting management tools.
One Month Before the Show
Finalise graphics and check for any last minute branding changes, since reprints become more expensive and harder to schedule closer to the show. Confirm your onsite point of contact for installation, and review the final floor plan against your approved concept.
Show Week
Installation typically takes place in the days immediately before the show opens. Confirm your builder's onsite schedule, check that meeting areas and technology are functioning as planned, and allow time for a final walkthrough before doors open to trade visitors.
Why This Timeline Matters More at ITB Berlin
Unlike some trade fairs where dates can shift slightly year to year, ITB Berlin's March dates are fixed well in advance, which removes some flexibility exhibitors might otherwise have. Because the show is fully business to business, a stand also needs to function as a working meeting space for the full duration, not just a display, which is why furniture, technology and staffing decisions
deserve as much planning time as the physical design itself.